Ongoing Projects

GENERAL PROCESS OF A PARTNERSHIP PROJECT

PPP Center – Receive Project Proposals

Conduct preliminary evaluation

30 days

Line Ministry

Conduct full feasibility study

Up to 6 months

Ministry of Economy and Development (MED)

Review and assess preliminary and full feasibility study conclusions

Within 5 working days after completion of the full feasibility study

Ministry of Finance

Review projects submitted by MED and provide opinions, conclusions, and approval

15 working days

Ministry of Economy and Development (MED)

Submit the project received from the Ministry of Finance for discussion at the Government meeting

5 working days

Government of Mongolia

Discuss the project and make a decision

Procurement / Selection Committee

Organize the competitive selection process

60 days

Government of Mongolia

Grant approval to conclude the contract

Total Duration

Overall implementation period of the PPP project

16 months (1 year and 5 months)